WHAT'S HOT
Prev | Current Page 37 | Next

"Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The Cross-Town Tunnels. Paper No. 1158"

The shafts, as shown on Plate XIV, were located in
the streets, but in such a way as to block only half of the roadway. At
the same time it was decided to construct in open cut about 200 ft. of
the Three-Track Tunnel at the west end of the contract in 32d Street,
where the rock surface was below the top of the tunnel. It was hoped
that the remainder of the work could be built without opening the
street, but further investigation showed that this was impracticable,
and eventually all the Three-Track Tunnel in 32d Street, except 120 ft.
east of the shaft, was built in open cut.
_Thirty-second Street Work in Tunnel._--Following the sinking of the
shaft, a drift was driven across the street at the crown of the tunnel,
and a top heading on the south side was excavated in both directions.
Frequent cross-drifts to the north side showed that the rock was nowhere
very sound and that, except for a short distance east of the shaft, it
was distinctly unfavorable for the wide Three-Track excavation. In this
stretch the north ends of these cross-cuts were connected by a second
heading, and wall-plates and sets of three-segment arch timbering were
set up to support the roof of the drifts. The cross-cuttings were
gradually widened and timbered until the entire excavation had been made
down to the level of the wall-plates, as shown in Fig.


Pages:
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49