having been minutely examined by the
competing contractors, the work was let to one of them for the sum of
L99,000. In order to drive the tunnel, it was deemed necessary to
construct eighteen working shafts, by which, like the heavings of a
mole, the contents of the subterranean gallery were to be brought to the
surface. This interesting work was in busy progress, when, all of a
sudden, it was ascertained, that, at about 200 yards from the south end
of the tunnel, there existed, overlaid by a bed of clay, forty feet
thick, a hidden quicksand, which extended 400 yards into the proposed
tunnel, and which the trial shafts on each side of it had almost
miraculously just passed without touching. Overwhelmed at the discovery,
the contractor instantly took to his bed; and though he was justly
relieved by the company from his engagement, the reprieve came too late,
for he actually died.
The general opinion of the several eminent engineers who were consulted
was against proceeding; but Mr. R. Stephenson offered to undertake the
responsibility of the work. His first operation was to lower the water
with which he had to contend, and it was soon ascertained that the
quicksand in question covered several square miles.